SIFANG creates a new substation construction speed record

Release Date:2016-07-14

The 130 MWP PV integrated substation of Xinyi Photovoltaic Agricultural Industrial Park is the EPC contractor project in the charge of SIFANG. The first phase construction consists of two 75000 kVA main transformers. This substation is completed in only 35 days from construction to power transmission. On Apr. 26, 2016, it successfully connected to the grid. A new record on the substation construction speed is created in the industry.

SIFANG Honghai completes a perfect project of high quality in the shortest period, which ensures successfully the interconnection transmission plan of the owner.